Vestas has announced three new turbine orders in Europe with a combined capacity of 191 MW. In Germany, Uhl Windkraft has ordered eleven V172-7.2 MW turbines for the Schnabelwaid project, providing 79 MW of capacity. Delivery is planned to begin in the first quarter of 2027, with commissioning expected from the third quarter of the same year. The project includes a 25-year service agreement.
Also in Germany, wpd has placed an order for the Reinstedt repowering project, comprising eleven V162-6.2 MW turbines and two V150-6.0 MW turbines, totalling 80 MW. Delivery is scheduled to start in the second quarter of 2026, with commissioning from the fourth quarter. The turbines will be supplied under a 15-year service agreement.
In Poland, Greenvolt Power Group has ordered eight V150-4.0 MW turbines for the 32 MW Lubień project. Delivery is planned to begin in the first quarter of 2027, followed by commissioning in the second quarter. The order includes a 20-year service agreement.