Koehler Paper, part of the Koehler Group, and Badische Stahlwerke (BSW) have decided not to proceed with plans to develop wind power projects at their sites in the port of Kehl, Germany, for the time being. The decision follows a joint feasibility study conducted with the port authority, which began in May 2024.

The companies commissioned more than ten external expert reports and invested over €400,000 in the study. These included assessments of wind conditions, wildlife conservation, noise and shadow flicker. The findings confirmed that wind turbines could be developed at the site in compliance with applicable permitting requirements.

However, both companies have since revised their site development plans. BSW needs additional land for the further development of its steelworks, including areas originally considered for wind turbines and their associated safety, assembly, crane and access requirements.

Koehler Paper also requires additional land to expand its mill in Kehl. The company recently announced a major investment to increase production capacity for premium playing card board.

In addition, the companies cited the lack of reliable long-term regulatory conditions for cost-effective self-generated electricity as a factor in their decision.

Use of cookies

Windtech International wants to make your visit to our website as pleasant as possible. That is why we place cookies on your computer that remember your preferences. With anonymous information about your site use you also help us to improve the website. Of course we will ask for your permission first. Click Accept to use all functions of the Windtech International website.