Hai Long offshore wind project in Taiwan completes constructionThe Hai Long offshore wind project in Taiwan has completed construction, with all 73 wind turbines connected to the electricity grid. The project is jointly developed by Mitsui, Northland Power and Gentari and has a total capacity of more than 1 GW.

A ceremony marking the completion of construction was held on 17 November 2026. It was attended by nearly 200 representatives from government, financial institutions and companies involved in the project.

The project brings together three offshore wind farms and was the first in the Asia-Pacific region to sign a contract for 14 MW offshore wind turbines.

Several Taiwanese companies contributed to the project. A total of 73 nacelles were procured, including 52 locally assembled units in addition to the original order for 21. This supported the expansion of Siemens Gamesa’s nacelle assembly facility in Taichung and brought nine additional Taiwanese suppliers into its approved supplier network.

Local companies also contributed to offshore installation, foundation manufacturing and onshore electrical infrastructure. These included CSBC-DEME Wind Engineering, Century Wind Power, CSBC Corporation, Taiwan, and TECO Electric & Machinery.

With construction complete, the project will proceed with the remaining administrative and permitting procedures ahead of full commercial operation, which is planned for 2027.

Use of cookies

Windtech International wants to make your visit to our website as pleasant as possible. That is why we place cookies on your computer that remember your preferences. With anonymous information about your site use you also help us to improve the website. Of course we will ask for your permission first. Click Accept to use all functions of the Windtech International website.