The European Commission has approved a Dutch state aid scheme to support the development of 2 GW of offshore wind capacity in the Netherlands. The scheme provides for two tenders, which will offer financial support, if required, for up to 15 years from the planned start of operations in 2032.
The scheme, with a budget of up to €9.45 billion, covers two offshore wind farms, IJmuiden Ver Gamma-A and Gamma-B, each with a planned capacity of 1 GW. The European Commission estimates that the two wind farms could generate up to 7,441 GWh of renewable electricity annually.
The Dutch government has scheduled both tender rounds to open on 26 November 2026 and close on 10 December 2026. The tender budgets are €4.758 billion for Gamma-A and €4.698 billion for Gamma-B, giving a combined maximum support budget of approximately €9.45 billion. The permits are expected to be awarded in the first quarter of 2027, with both wind farms planned to enter operation in 2032.