Phase 1 of the Vifor wind farm in Buzău County, Romania, has entered its trial operation phase, adding 192 MW of generation capacity. Phase 1 comprises 30 Vestas V162-6.4 MW turbines.

Construction of Phase 2 is already under way and will increase the project’s total capacity to 461 MW. Commissioning of the full project is scheduled for summer 2027.

Use of cookies

Windtech International wants to make your visit to our website as pleasant as possible. That is why we place cookies on your computer that remember your preferences. With anonymous information about your site use you also help us to improve the website. Of course we will ask for your permission first. Click Accept to use all functions of the Windtech International website.