Swift Current Energy (Swift Current) has signed an agreement with the Nordex Group to purchase 41 N149/4.X wind turbines for Swift Current’s 196MW Castle Gap Wind Project in Mills and Lampasas Counties, Texas, USA.
 
Both parties have also signed a service contract covering five years of operations and maintenance. The Nordex Group will supply the turbines on tubular steel towers with a hub height of 108 metres. Delivery and installation of the turbines is scheduled for summer 2022 with commissioning of the turbines planned for the end of the same year.