In the fourth quarter of 2025, Nordex Group secured orders totalling 3,552 MW in its projects segment, excluding service activities. This represents an increase of about 9.2 per cent compared with the same period in 2024, when orders reached 3,253 MW.

For the full year 2025, Nordex Group recorded total project orders of 10,214 MW, up 22.5 per cent from 8,336 MW in 2024. The average sales price per MW remained broadly stable. In the fourth quarter of 2025, the average sales price was €0.89 million per MW, unchanged from the same period a year earlier. For the full year, the average sales price increased slightly to €0.91 million per MW, compared with €0.90 million per MW in 2024, mainly due to differences in project scope and regional mix.

Between October and December 2025, customers ordered 577 wind turbines for projects across 12 countries. Most of the orders came from Germany, Canada and France.

Use of cookies

Windtech International wants to make your visit to our website as pleasant as possible. That is why we place cookies on your computer that remember your preferences. With anonymous information about your site use you also help us to improve the website. Of course we will ask for your permission first. Click Accept to use all functions of the Windtech International website.