CJR Renewables is nearing completion of the Balance of Plant works for a 165 MW renewable energy project in Chile. The company’s scope includes civil and electrical works such as the construction of foundations and platforms, access roads and the installation of medium-voltage networks, primary transmission lines and communications infrastructure.
The project also includes the construction of a 33/220 kV substation and installation of a 220 kV high-voltage transmission line to support grid integration.