Latest Issue
 
Windtech International March April 2024 issue

 

FOLLOW US AT

follow

 

follow


NordSeeOneInnogyThe rotor for the 27th wind turbine was successfully installed last week at the Nordsee One construction site, located approximately 40 kilometres north off the island of Juist. This marks the halfway point for turbine installation at the 332MW wind farm. Turbine installation will continue in parallel with the progressive commissioning of the wind turbines.

All 54 foundation monopiles and transition pieces, as well as the offshore substation and infield cables, were successfully installed in 2016. The project team expects the installation and commissioning of all 54 Nordsee One turbines to be completed by the end of 2017. Once completed, the Nordsee One wind farm will consist of 54 Senvion 6.2M126 wind turbines, with an overall installed capacity of 332MW. Nordsee One is owned by Northland Power Inc. (85%) and innogy SE (15%).

 
Use of cookies

Windtech International wants to make your visit to our website as pleasant as possible. That is why we place cookies on your computer that remember your preferences. With anonymous information about your site use you also help us to improve the website. Of course we will ask for your permission first. Click Accept to use all functions of the Windtech International website.