Gamesa has signed an agreement to supply 54MW of turbines to the San Lorenzo wind farm being constructed by Japan’s Kanematsu Corporation at Guimaras Island, Chile.
 
Under the terms of the agreement, Gamesa will handle the supply, assembly and commissioning of 27 of its G90-2.0MW turbines at the facility. In addition, Gamesa will maintain the wind farm for six years, with option for renewal. The turbines are slated for delivery over the course of 2014 and the project is expected to be fully commissioned by the end of next year.
 
Use of cookies

Windtech International wants to make your visit to our website as pleasant as possible. That is why we place cookies on your computer that remember your preferences. With anonymous information about your site use you also help us to improve the website. Of course we will ask for your permission first. Click Accept to use all functions of the Windtech International website.