Vestas has received an order for 269 MW of turbines, consisting of three V110-2.0 MW turbines, 22 V120-2.2 MW turbines, and 51 V150-4.2 MW turbines for a wind project in the U.S. Including previously purchased 2 MW platform components, the project has a total nameplate capacity of 299 MW.
 
The order includes supply and commissioning of the turbines as well as a 10-year service agreement. Turbine commissioning is scheduled for the fourth quarter of 2020. The project and customer are undisclosed.
 
Further Vestas has received an order for 183 MW of V120-2.2 MW turbines for a wind project in the U.S. with a number of turbines operating in 2.0 MW. Including previously purchased 2 MW platform components, the project has a total nameplate capacity of 202 MW. The order includes supply and commissioning of the turbines as well as a 10-year service agreement. Turbine delivery will begin in the second quarter of 2020 with commissioning scheduled for the fourth quarter of 2020. The project and customer are undisclosed.