The Finnish Government has designated four areas in its exclusive economic zone for offshore wind power development. It has also issued a decree setting out the competitive tendering process and proposed new rules for the construction and decommissioning of offshore wind farms. The four designated areas are Selkämeri länsi (Bothnian Sea West), Selkämeri itä (Bothnian Sea East), Perämeri etelä (Bothnian Bay South) and Perämeri pohjoinen (Bothnian Bay North).
A developer will be selected for each area through a competitive tender. The successful bidder may then apply for an exploitation permit to carry out further studies and obtain the permits required for the project.
Perämeri etelä will be the first area put out to tender, followed by the other three. The Energy Authority could launch the first tender in the first half of 2027. The process will not involve state aid, and projects may take 10–15 years to progress from tendering to electricity generation.
The tender evaluation will give equal weight to the price offered and qualitative criteria. Participants and successful bidders will also be required to provide securities. The performance security will increase as projects progress, starting at a relatively low level during the early development stages.
The Government has also proposed amendments to the Water Act covering construction, decommissioning and financial security in the exclusive economic zone. Offshore wind farms would generally have to be fully dismantled at the end of their operational life, although the Finnish Supervisory Agency could determine on a case-by-case basis how much of the structures must be removed at seabed level.
The proposals aim to ensure that developers remain responsible for decommissioning costs under the polluter pays principle. The proposed legislation is expected to enter into force in spring 2027.