Senvion has commissioned 14 of its 2MW MM100 turbines for a second wind farm around the city of Nowy Staw, which is located about 50 kilometres south-east of Gdańsk.

Both wind farms are operated by RWE Innogy. The installation of the  turbines started in August 2015 and the installation team finished assembly at the end of September. At October 16th, all turbines were operational and in December the permit of use was handed over.

Senvion commissions wind project in Poland

Senvion has commissioned 14 of its 2MW MM100 turbines for a second wind farm around the city of Nowy Staw, which is located about 50 kilometres south-east of Gdańsk. Both wind farms are operated by RWE Innogy. The installation of the turbines started in August 2015 and the installation team finished assembly at the end of September. At October 16th, all turbines were operational and in December the permit of use was handed over.