SHC WennerstorfAs part of the regular validation and certification process for its turbines in the Delta4000 series, the Nordex Group has replaced the gearboxes first installed in two N149/4.0-4.5 turbines in Wennerstorf, Lower Saxony, Germany. The turbines installed at this site in 2018 are the first Delta4000 turbines of this model.
 
The turbines have been in operation since August and November 2018 respectively and are subjected to a detailed assessment of their condition after the first 15 and 24 months of operation. To this end, the manufacturer expertly dismantles the gearboxes into all individual parts in order to perform a qualified assessment with the bearing manufacturers and Nordex experts. The aim is to ensure the theoretically determined reliability and to incorporate early findings from the operation of the gearboxes into the series production.
 
The drive train is designed in such a way that gearboxes from different manufacturers can be installed. These planned gearbox exchanges give the Nordex Group an opportunity to install gearboxes from different manufacturers and to test and compare their behaviour and efficiency in real operation.
 
In the Wennerstorf wind farm the first turbine gearbox was exchanged in February 2020 and the second one in an adjacent turbine was now replaced in September as planned. Nordex used a so-called "self-hoisting crane (SHC)", which is installed on the turbine's nacelle, to exchange the gearboxes. This self-hoisting crane climbs up the turbine tower on its own hoist rope and installs itself on the topside of the nacelle.
Use of cookies

Windtech International wants to make your visit to our website as pleasant as possible. That is why we place cookies on your computer that remember your preferences. With anonymous information about your site use you also help us to improve the website. Of course we will ask for your permission first. Click Accept to use all functions of the Windtech International website.