Vestas has secured a 50MW order for the Sandy Knowe wind project from ERG. The project will be located in Scotland and will feature 14 V112-3.45 MW turbines in 3.6MW power mode.
 
The contract further includes supply, installation and commissioning of the wind turbines, as well as a 20-year service agreement. Turbine deliveries are expected to begin in the third quarter of 2021, while commissioning is planned for the fourth quarter of 2021.
Use of cookies

Windtech International wants to make your visit to our website as pleasant as possible. That is why we place cookies on your computer that remember your preferences. With anonymous information about your site use you also help us to improve the website. Of course we will ask for your permission first. Click Accept to use all functions of the Windtech International website.