Nordex SE has received an order from Volkswind France SAS to supply and install the Haut Plateau Picard wind farm with eleven turbines from the N100/2500 series, which Nordex will install in spring 2015.

Grid connection and the handover of the wind farm are scheduled latest for October 2015. This is also when the 15-year Premium Service Agreement, which is an integral part of the transaction, comes into effect.

 
Use of cookies

Windtech International wants to make your visit to our website as pleasant as possible. That is why we place cookies on your computer that remember your preferences. With anonymous information about your site use you also help us to improve the website. Of course we will ask for your permission first. Click Accept to use all functions of the Windtech International website.