VBMS has been awarded an inter-array cabling contract with a value of approximately € 80 million for the 500MW EnBW Hohe See Offshore Wind Farm.

The contract includes the supply, installation and burial as well as termination and testing of seventy nine 33kV inter-array cables. The project execution will commence in 2017 with cable installation activities scheduled for 2018 and 2019.

Use of cookies

Windtech International wants to make your visit to our website as pleasant as possible. That is why we place cookies on your computer that remember your preferences. With anonymous information about your site use you also help us to improve the website. Of course we will ask for your permission first. Click Accept to use all functions of the Windtech International website.