Korean Electric Power Corporation (KEPCO) has via Fujeij Wind Power Company placed an order for 27 V126-3.3MW wind turbines to build the 89MW Fujeij wind farm in Al Shobak, Governorate of Ma'an, Jordan.

In addition to turbine installation and a 20-year full-scope Active Output Management 5000 (AOM5000) service agreement, the Engineering, Procurement and Construction (EPC) contract also includes the engineering, civil and electrical works to connect the power plant to the grid. Wind turbine delivery is planned to begin in the fourth quarter of 2017, whilst commissioning is expected for the third quarter of 2018.

Use of cookies

Windtech International wants to make your visit to our website as pleasant as possible. That is why we place cookies on your computer that remember your preferences. With anonymous information about your site use you also help us to improve the website. Of course we will ask for your permission first. Click Accept to use all functions of the Windtech International website.