Polenergia has been the first operator in Poland to obtain from the Regional Directorate of Environmental Protection (RDOŚ) in Gdansk the environmental permit for the construction of the offshore wind farm Baltic Środkowy III with a planned capacity of 600MW.

The roadmap provides for a three-year period to prepare the technical design and to obtain building permission. Commencement of construction is expected in 2019. The first electricity is expected to flow into the Polish grid within 5 years (2021-2022).

Use of cookies

Windtech International wants to make your visit to our website as pleasant as possible. That is why we place cookies on your computer that remember your preferences. With anonymous information about your site use you also help us to improve the website. Of course we will ask for your permission first. Click Accept to use all functions of the Windtech International website.