EDF Renewable Energy (EDF RE) has announced that the 194MW Spinning Spur 3 Wind Project in Texas reached commercial operation three months ahead of schedule on Sept. 28, 2015.

The clean electricity generated from the Spinning Spur 3 Wind Project will be provided to two municipal utilities, Georgetown Utility Systems and Garland Power & Light, under long-term Power Purchase Agreements. The Project, located 50 miles west of Amarillo in Oldham County, commenced construction of its 97 Vestas V-100 2 MW wind turbines in October 2014 and feeds into the CREZ (Competitive Renewable Energy Zone) transmission infrastructure.

Use of cookies

Windtech International wants to make your visit to our website as pleasant as possible. That is why we place cookies on your computer that remember your preferences. With anonymous information about your site use you also help us to improve the website. Of course we will ask for your permission first. Click Accept to use all functions of the Windtech International website.