On Thursday 4 May the transformer was installed in Offshore Windpark Q7.

.
This substation had arrived on 1 May in IJmuiden harbour on the Northwest coast of the Netherlands. It weighs over 500 tonnes, measures 10 by 20 metres and is 12.5 metres tall. At arrival in IJmuiden the colossus had been en route for two days from Aalborg in Denmark. This is the first transformer station to be installed at such a distance at sea. By now all 61 foundations and transition pieces of Q7 windpark have been installed and a start has been made with sea and land cabling. The production and installation of the wind turbines will be completed in September 2007.
Use of cookies

Windtech International wants to make your visit to our website as pleasant as possible. That is why we place cookies on your computer that remember your preferences. With anonymous information about your site use you also help us to improve the website. Of course we will ask for your permission first. Click Accept to use all functions of the Windtech International website.