Vestas has received a 240MW order to repower the Big Sky Wind project in Illinois, USA, owned by Vitol Wind.
 
The order consists of 104 V120-2.2MW turbines and five V110-2.0MW turbines in 2.2MW operating mode, which will replace the project’s current technology of 109 Suzlon S88-2.1MW turbines. The order includes supply and commissioning of the turbines, as well as a 20-year service agreement. Turbine delivery for the orders begin in the fourth quarter of 2021 with commissioning scheduled for the second quarter of 2022.
Use of cookies

Windtech International wants to make your visit to our website as pleasant as possible. That is why we place cookies on your computer that remember your preferences. With anonymous information about your site use you also help us to improve the website. Of course we will ask for your permission first. Click Accept to use all functions of the Windtech International website.