Changhua OWF Onshore cable installation worksIn a first phase, the consortium executes the onshore cable installation works to connect the existing onshore sub-station to the cable interface near shore. The onshore cables are currently being installed in an underground track of 13 kilometres of duct banks. For these construction works, 2 kilometres of horizontal directional drillings are performed over 13 different locations and 45 prefabricated manholes are installed.

Onshore works will take 20 months and are executed by the Taiwanese subcontractor Star Energy Corporation. The connecting submarine cable will be installed in the course of 2020. The Changhua Offshore Wind Farm contract was awarded to the Consortium Jan De Nul-Hitachi on 30 April 2018. The project entails the manufacturing and installation of 21 5.2MW offshore wind turbines for the Changhua Offshore Wind Farm, off the coast of Fangyuan in Central Western Taiwan. Jan De Nul Group is responsible for the design, fabrication and installation of the foundations, the installation of the wind turbines, the supply and installation of the cables off- and onshore as well as for the upgrading of the substation. Hitachi Ltd. is in charge of manufacturing, assembly, operation and maintenance (O&M), and other works related to the offshore wind turbines with downwind rotor. Manufacturing of the wind turbines is planned mainly during 2019 in order to deliver them in early 2020. Test operation of the equipment is targeted to start in the summer of 2020, and the completion is scheduled for the end of December of the same year.
Use of cookies

Windtech International wants to make your visit to our website as pleasant as possible. That is why we place cookies on your computer that remember your preferences. With anonymous information about your site use you also help us to improve the website. Of course we will ask for your permission first. Click Accept to use all functions of the Windtech International website.