Peikko Norge has received an order to deliver rock foundation technology to the Marker Wind Park, located in the Ørje area of south-east Norway.

Peikko will deliver all the steel components for all 15 foundations at the wind farm. The deliveries comprise FATBAR Rock Anchors, tower adapter plates, drilling templates, and foundation reinforcement. Peikko is also responsible for the foundation design and structural calculations. The deliveries are scheduled to take place between April and August 2018. The wind park is estimated to be operational by the end of 2018. Vestas will deliver fifteen V136-3.6MW turbines, with a hub height of 142 meters.

Use of cookies

Windtech International wants to make your visit to our website as pleasant as possible. That is why we place cookies on your computer that remember your preferences. With anonymous information about your site use you also help us to improve the website. Of course we will ask for your permission first. Click Accept to use all functions of the Windtech International website.