Terna Energy, member of the GEK TERNA Group, announces the completion and commencement of commercial operations of the Fluvanna I Wind farm in Scurry County, Texas, USA.

Its construction began in December 2016 and was completed in less than 12 months. Fluvanna I has a total capacity of 155.4MW and consists of 74 wind turbines (Siemens Gamesa) of 2.1 MW and it will deliver electricity into the Texas Interconnection power grid. For the funding and completion of the project Terna Energy partnered with Copenhagen Infrastructure Partners (CIP), as well as with a consortium of banks. The total cost of the investment reaches US$ 250 million.

Use of cookies

Windtech International wants to make your visit to our website as pleasant as possible. That is why we place cookies on your computer that remember your preferences. With anonymous information about your site use you also help us to improve the website. Of course we will ask for your permission first. Click Accept to use all functions of the Windtech International website.