The erection of 80 AREVA wind turbines was successfully completed at the Global Tech I wind farm with the last rotor star installation finalised Friday August 29.

The wind farm of roughly 41 square kilometres is located 100 kilometres off the coast in the German North Sea. AREVA’s 5 Megawatt M5000-116 turbines were manufactured at the Group’s Bremerhaven and Stade sites, in northern Germany. The commissioning of turbines can begin when the grid connection is available. The Group’s installed base now reaches 630 MW for offshore wind.

Use of cookies

Windtech International wants to make your visit to our website as pleasant as possible. That is why we place cookies on your computer that remember your preferences. With anonymous information about your site use you also help us to improve the website. Of course we will ask for your permission first. Click Accept to use all functions of the Windtech International website.