Britain's seas ‘Open for Business' |
|
|
|
Friday, 06 June 2008 |
|
The Crown Estate has identified zones for
development, which after further review they expect to allocate to developers
next year.
After this they will then work with the developers to identify
specific sites within the zones. This allocation process will be based on the
Strategic Environmental Assessment (SEA) being carried out by BERR, which will
examine issues such as the impact on wildlife and habitat, shipping lanes and
fishing, with the zones being adjusted to reflect the SEA findings. Once the
zones have been finalised the Crown Estate will co-invest with developers in
the development process leading to planning. It is expected that by 2013
individual sites will start to receive planning permission, with the first
phases of the new wind farms becoming operational in 2015.
|